Vietnam released its 2026 energy security report at a national forum in Hanoi on November 10. Báo Điện tử Chính phủ (Government News) reported that the document recorded a national peak power load of 57,537 megawatts on June 24.
The report estimated electricity generated and imported during the full year at 356.2 billion kilowatt-hours, up 10.3%. That is a forecast made when the report was released, not a final annual total. Megawatts measure power at a point in time, while kilowatt-hours measure energy over a period.
Figures in the report
The northern region’s peak load reached 30,248 MW, Government News reported. The document said there had been no rotating power cuts nationwide during the period assessed and put growth in commercial electricity sales in the first ten months at 9.84%.
It also reported the start of 136 grid projects and energisation of 131 during the first nine months. These are observations for the reporting period and do not guarantee that future interruptions will not occur.
The next planning cycle
The report described energy security in 2027 as challenging, with electricity demand expected to keep rising. It forecast a northern peak load of between 32,693 and 34,865 MW in 2027. That range is a projection, not an observed result.
Its six sections address energy security’s role, policy, results and challenges, the energy outlook, proposed measures and recommendations. Suggested directions include reducing import dependence, developing infrastructure, improving institutions, training workers and international cooperation.
The forum also introduced plans for a dedicated energy security information page. Proposed policies and projects will require their own implementation steps.