Hanoi has asked departments and local authorities to accelerate public-investment disbursement, review delayed projects and update growth scenarios for the final two months of 2026. The directions appear in city People’s Committee Notice 1889/TB-UBND dated November 11.
The Government Electronic Newspaper said the notice records conclusions from a November 6 committee meeting chaired by Vũ Đại Thắng. Hanoi continues to target GRDP growth of at least 11% for 2026. That is a full-year target, not an achieved result.
Ten-month figures and growth review
The city reported third-quarter GRDP growth of 10.02%. In the first ten months, industrial production rose 9%, total retail goods sales and consumer-service revenue rose 16.2%, and exports increased 8.6% from the same period a year earlier.
By October 31, local state budget revenue reached VND652.790 trillion and public-investment disbursement was VND125.444 trillion. Both are cumulative figures through the end of October, not increases recorded solely in November.
The Finance Department must work with the city statistics office and other agencies to update data, review scenarios and assess each sector’s potential contribution. Its report is due before November 29 to support the 2026 estimate and 2027 scenarios.
Checking finance and projects
The city asked investors to connect disbursement with actual completed construction. Its assessment said advances remained a significant share of funds paid out, while payments for completed construction were not proportionate. Investors must review advances and settle eligible accepted work.
During November, authorities are to review major ring roads, Red River bridges, urban rail, drainage and environmental projects. They must identify packages that can add shifts and have work accepted before year-end.
For five urban rail lines already started, the rail management board must review progress, financing needs and funding options. Local authorities are responsible for preparing relevant land, especially at stations. Agencies must track progress weekly and address obstacles within their assigned responsibilities.