Vietnam's Construction Ministry has asked the investor and contractors to accelerate work on the second component of the first phase of the Khánh Hòa–Buôn Ma Thuột expressway. The ministry put completed work at about 81.3 percent of the component's contracted volume.

Government News reported the instruction on November 13. The ministry requested additional workers, machinery and financial resources, with outstanding bridge, asphalt and traffic-safety work targeted for completion before December 31, 2026. That deadline is an instruction, not evidence that the whole expressway is already open.

Different deadlines for tunnel tubes

For the left tube of the Phượng Hoàng tunnel, the ministry requested a concrete road surface before November 30 and mechanical, lighting and fire-safety work before December 20. For the right tube it set separate targets: the lining before December 10, the concrete surface before December 25 and the remaining mechanical and safety systems before February 2027.

Roadbed and slope reinforcement at both tunnel portals are targeted before December 25, 2026. The Railway Project Management Board was asked to direct contractors to prepare a detailed revised schedule for work affecting progress.

The ministry cited shortages of suitable stone and labor, higher asphalt prices and rainy weather among the difficulties. Disbursement on the second component was also below the national average, according to its report.

Project-wide timetable

The first-phase expressway is 117.5 kilometers long across Khánh Hòa and Đắk Lắk and consists of three components. Its total investment is 21.935 trillion đồng, including 9.818 trillion đồng for the second component under the Construction Ministry.

A 20-kilometer stretch opened at the end of May 2025. The reported plan calls for the remaining sections to be substantially completed in 2026 and the project to enter synchronized operation in 2027. The 81.3 percent figure applies to component two, not to the whole route.