Công ty Cổ phần Điện mặt trời Srepok 3, a KN Holdings member, broke ground on the KN Srêpốk 3 floating solar plant in Đắk Lắk on 28 November. VnExpress reported a design capacity of 304 MW and investment of more than VND 7.661 trillion, with operation targeted for the fourth quarter of 2027.

The provincial authorities approved the investment policy and investor in March 2026. Groundbreaking marks the start of the project, not completion or commercial generation. The approximately 605 million kilowatt-hours expected each year is an estimate for when the plant operates.

Solar equipment on a reservoir

The project is planned for about 354 hectares of water surface at the Srêpốk 3 hydropower reservoir. The operating area and transformer station account for roughly another six hectares. The plans include a 35/500 kV step-up substation with 375 MVA proposed capacity and a 500 kV transmission line connecting to the national grid.

The developer also describes battery storage with power equivalent to 10% of the plant’s capacity and two hours of storage. This is the stated configuration in the project plan; construction and commissioning must establish what is ultimately delivered.

Working on a reservoir requires suitable floats, anchoring, panels and electrical equipment. VnExpress reported that the project would select equipment for the water environment. Long-term performance will depend on construction, testing and actual operation.

The next milestones

The developer estimates that the plant could contribute more than VND 170 billion a year to the local budget once operating. That is a projection, not revenue already collected. Provincial leaders expressed hopes for additional renewable power and jobs.

Construction progress, grid connection and the actual start date can be assessed against the late-2027 target. Related coverage includes the review of rooftop solar policy and Vietnam’s 2026 energy security report.