Vietnam disbursed VND717.1613 trillion in state-budget public investment from the start of 2026 through 5 November, equal to 74.37% of the plan assigned by the prime minister, according to a finance ministry report published by the Government News on 12 November.
The cumulative total was VND691.8232 trillion a week earlier, on 29 October. Disbursement during the following week was therefore VND25.3381 trillion. The ministry issued the weekly report on 11 November.
Assigned and allocated funds
The National Assembly approved VND1,105.8234 trillion in state-budget public investment for 2026. The plan assigned by the prime minister amounted to VND964.3543 trillion. Local authorities added VND59.2237 trillion from balanced local budgets, bringing the total plan assigned by the reporting date to VND1,023.5779 trillion.
Ministries, central agencies and local authorities had allocated VND1,007.3937 trillion to specific tasks and projects, including the local additions. Excluding those additions, detailed allocation reached 98.3% of the prime minister’s plan. Allocation and disbursement are separate stages.
Uneven progress
Six ministries and central agencies and 16 localities had disbursement rates at or above the national average. Five central bodies were below 20%, including the Vietnam Cooperative Alliance, which had not disbursed funds in the report.
The ministry also calculated a 76.8% rate after excluding a planned local-budget saving for the Lào Cai–Hà Nội–Hải Phòng railway. That figure uses a different denominator from the 74.37% headline rate.