Son La province held a groundbreaking ceremony for the Dong Phu Yen pumped-storage hydropower project in Muong Bang commune on November 14. VietnamPlus reported that Xuan Thien Ninh Binh is the developer and that planned investment is nearly VND28 trillion. Plans call for four generating units totalling 1,200 MW in Muong Bang and Muong Coi communes.
Two reservoirs and a grid connection
The design includes an upper reservoir and a lower one, each with usable capacity of 6.5 million cubic metres and a design head of about 600 metres. The generating station and waterway are planned inside the mountain. Close to 10 kilometres of 500 kV line would link the facility to the Son La–Viet Tri transmission corridor.
Pumped storage moves water uphill to store energy, then releases it through generating units when needed. The project is intended to support grid balancing and reserve capacity in northern Vietnam after it is completed.
Construction phases and land work
The first phase is planned for 900 MW from 2027 to 2030. The second covers 300 MW from 2031 to 2032. The detailed schedule places the start of first-phase construction in the fourth quarter of 2027, following the November 2026 ceremony.
The project covers more than 425 hectares, most of it in Muong Bang. VietnamPlus reported that the commune had inventoried land and assets of 70 households, individuals and organisations in more than 70 hectares associated with the first phase and ceremony site. The province approved the investment policy on August 30, 2026.