Long Sơn Petrochemicals is targeting a restart of its complex in the second quarter of 2027 after a production suspension. Sài Gòn Giải Phóng reported the company’s November 11 announcement that it was accelerating an ethane feedstock project and a comprehensive maintenance programme.

Production was suspended from late May 2026 after disruption to Middle Eastern feedstock supplies, the report said. The restart and commissioning dates are company plans, not confirmation that operations have resumed.

Feedstock upgrade

The LSPE enhancement project has an estimated investment of $500 million. The company plans to introduce ethane imported from the United States, gradually increase output and complete commissioning by the end of the third quarter of 2027, according to the newspaper.

The complex has a design capacity of 1.4 million tonnes of polyolefin resin a year. Design capacity should not be mistaken for actual production during a restart year.

In a September 2026 update, LSP said it had signed a long-term agreement for one million tonnes of US ethane annually and long-term charters for five ethane carriers. It said construction of two refrigerated tanks, each with capacity of about 55,000 tonnes, was more than 60% complete at that time.

Separate milestones

LSP’s September update had put overall enhancement-project completion at the end of 2027. The November report gives a third-quarter commissioning target after a planned second-quarter restart. The statements concern different milestones and were made at different times.

LSP says the upgrade is intended to broaden its feedstock options. Expected cost and emissions benefits remain company expectations until performance is established after operation.