Vietnam’s Ministry of Construction has ordered a comprehensive review of preparations for the first phase of Long Thành airport. Airports Corporation of Vietnam must submit its findings to the ministry and the civil aviation authority before November 15, Báo Điện tử Chính phủ (Government News) reported.
ACV previously submitted a plan to the aviation authority targeting operations from 00:00 local time on December 24. That date is part of the operator’s proposal, while inspections, acceptance and aviation approvals remain to be completed in accordance with the rules.
Construction and operational readiness
The ministry asked ACV to work with the aviation authority and other agencies on a feasible plan covering security and safety. The review must examine progress on construction packages and the conditions needed before the airport can operate.
Government News said construction completion must be coordinated with acceptance procedures, legal paperwork and sector-specific approvals. The review must also consider the operational readiness and airport transfer programme, known as ORAT, alongside the proposed operating plan.
The Civil Aviation Authority of Vietnam must assess ACV’s submission and report to the ministry before November 18. The ministry plans a further meeting on preparations during November.
Access roads under review
Agencies responsible for road infrastructure and construction investment were asked to check progress on connecting expressways, national highways and provincial roads. Their report on access is due before November 16.
ACV has also informed airlines so they can prepare their operating plans. These are preparation steps and reporting deadlines, not evidence that commercial flights have already begun at Long Thành.