The Thanh Hóa–Sầm Sơn 220 kV transmission line was successfully energised on November 11. National Power Transmission Corporation EVNNPT said the operation took place at 13:44 local time with the project manager, the northern electricity dispatch centre and other units coordinating.

The line is one component of a project that also includes the Sầm Sơn 220 kV substation. The line’s energisation is a completed milestone, while work on the substation continues.

A 40.1 km connection

EVNNPT said the newly built double-circuit line connects the Thanh Hóa 500 kV substation with the Sầm Sơn 220 kV substation. It is about 40.1 km long and crosses 11 communes and wards in Thanh Hóa province.

EVNNPT is the project investor and the Central Power Projects Management Board manages implementation. Power Transmission Company No. 1 is expected to take over operation after completion.

An investor-level acceptance council met on November 4 and agreed to energise the line, EVNNPT said. The operation was then completed on November 11.

Substation work remains

The Government Electronic Newspaper classifies the line as a class-I energy work within the group-B project for the substation and its connecting line. The line has been energised, while construction teams continue to work on the remaining substation components.

EVNNPT describes the operation as one milestone in the wider project. It says the teams remain focused on the quality and safety of the outstanding work.

The transmission company expects the project to strengthen supply capacity in Thanh Hóa, especially the eastern part of the province, and improve regional system reliability. Its actual performance will require monitoring once the associated components enter service.