The Lai Uyên 220 kV substation and its connecting lines in Bàu Bàng commune, Ho Chi Minh City, were successfully energised at 21:53 on 21 November, according to the National Power Transmission Corporation (EVNNPT). The project adds a connection point serving the northern part of the city and surrounding areas.
EVNNPT is the investor, while its Southern Power Project Management Board (SPMB) managed implementation. Power Transmission Company No. 4 is responsible for operation. The Government Portal says the site was previously in Lai Uyên township, Bàu Bàng district, Bình Dương province, before the current administrative designation.
One transformer installed in this phase
The new 220/110 kV substation has a planned configuration of two 250 MVA transformers. The current phase installs one 250 MVA unit, AT1, and reserves space for the second. The two-unit figure therefore describes the project's design, not two transformers already installed.
Six of the 10 planned 220 kV bays and six of the 15 planned 110 kV bays receive equipment in this phase. Control, protection, measurement and communications equipment is provided alongside a remote monitoring and control system.
Two double-circuit 220 kV connecting sections, about 520 metres long in total, link the station into the existing Chơn Thành–Bến Cát–Mỹ Phước line. They connect both circuits of that line to the new station.
Improving the regional network
EVNNPT says the energisation will support electricity demand in Ho Chi Minh City and nearby areas while helping relieve existing 220/110 kV transformers and 110 kV lines. The Government Portal also says the project contributes to the N-1 reliability criterion. Those are stated operating aims; the sources do not provide a measured reduction in network load.
For other transmission projects, KBVN+ has reported on the Thanh Hóa–Sầm Sơn 220 kV line and the Bạc Liêu connection to the Cà Mau–Sóc Trăng network.