Vietnam's National Assembly voted on November 13 to end implementation of two earlier resolutions on investment in the Ho Chi Minh Road. Government News reported that 465 of the 466 deputies taking part supported the resolution.

The vote concerns resolutions adopted in 2004 and 2013. Construction Minister Trần Hồng Minh told lawmakers that closing the phased two-lane investment program should be distinguished from finishing every remaining part of the route and its associated work.

Sections still to be completed

The government report presented to the Assembly said the plan to achieve basic connectivity by the end of 2026 uses National Highways 32 and 21 for parts of a route totaling more than 2,656 kilometers. It said 2,499 kilometers had been completed by 2025 and projected another 144.5 kilometers would be completed during 2026.

A further 13 kilometers is open on a gravel base and is expected to be completed in the first quarter of 2027. The end of the earlier investment resolutions therefore does not mean that every section was finished on the day of the vote.

Financial settlement of the first phase was completed in 2016. For the second phase, settlement approval covered construction work on 1,017 of 1,138 kilometers, or 89.4 percent. The government expects the remaining settlement work to be finished in 2027.

Work beyond the initial phase

The government said unresolved compensation, support and resettlement matters would continue to be addressed, alongside local connections. The minister also discussed possible future upgrades, including expressway-standard sections consistent with approved plans.

That discussion is a direction for later work. The November 13 resolution itself closes implementation of the two earlier investment policies and should not be treated as approval of a new expressway project.